2014 Report details for project: Typhoon

Project name: Typhoon - there are 3 reports for this project: 2013, 2014, 2015
Google search: Google search on project name (opens in new window) opens in new window
Organisation: MOD (D17) - see all reports for this organisation
Report year: 2014 (data is from Sept 2013)
Category: Military - see all reports for this category
Description: The Typhoon Programme aims to deliver an agile multi-role fighter that is capable of providing 75% of UK’s combat aircraft (ac). Typhoon is being delivered in 3 Tranches of ac: Tranches 1 and 2 have now all been delivered with the Tranche 3 delivery profiled between December 2013 and April 2018. The current delivery programme has the following major elements: Future Capability Programme 1 - to deliver a multi-role, dual-mode precision guided bomb capability to Tranche 2 and 3 ac; Future Capability Programme 2 - to deliver Meteor, Stormshadow and Brimstone 2 to Tranche 2 and 3 ac; advanced radar - to deliver increased capability to Tranche 3 ac, specifically Electronic Attack, Day/Night/All weather targeting and full exploitation of Meteor; and Typhoon Future Synthetics - to improve synthetic training capability and enable Air Command's intent to reduce the volume of live training flying.
DCA (RAG): Amber/Green
DCA text: Funding of future upgrades to ensure that Typhoon delivers its required capability outputs is being progressed through the approvals process. Additionally further future capability requirements are being considered to ensure that Typhoon remains credible. Shared development opportunities with export partners are being considered.
Start date: 1987-11-06
End date: 2024-03-30
Schedule text: The first phase of the Future Capability Programme has shown good progress over the past year now that the project schedule has been rebaselined, through joint working between the Department and industry. This accommodated the 18-month delay which was highlighted in Major Projects Report 2012. The Typhoon front line fleet continues to build with well over half of the contracted deliveries of 160 aircraft in three tranches now in service with the Royal Air Force. Typhoon Tranche 2 has been declared as multi-role ready for training to further enable the development of the Typhoon Force.
Baseline: £1,215.66m
Forecast: £1,215.57m
Variance: -0.01%
Variance text: N/A
Whole Life Cost: £20,147.01m
WLCost text: Work is ongoing to ensure that whole life costs remain within budget. The Fast Air Support Team (FAST) Integrated Transformation activity aims to reduce programme costs whilst allowing recycling of financial headroom to further develop the aircraft.
Notes1:
Notes2:
Sourcefile: IPA_2014.csv