2015 Report details for project: SLC Transformation Programme

Project name: SLC Transformation Programme - there are 2 reports for this project: 2014, 2015
Google search: Google search on project name (opens in new window) opens in new window
Organisation: BIS (D3) - see all reports for this organisation
Report year: 2015 (data is from Sept 2014)
Category: Transformation - see all reports for this category
Description: The objectives of the programme are: • Introduce a modern, integrated and flexible IT system to enable the safe delivery of HE reform (including changes to borrowers’ repayment terms including variable interest rates); • Enhance customer service and operational efficiency; and • Support the transformation of SLC’s business through introduction of a unified technology platform and the standardisation of processes.
DCA (RAG): Amber/Red
DCA text: Following a review of the programme the Board approved a re-set. Action was initiated to revise the Roadmap, Business Case and benefits realisation plan. Governance has been reshaped.
Start date: 2012-03-19
End date: 2017-03-31
Schedule text: As a result of the changed priorities in the reset programme, planned schedule, benefits and costs will be impacted
Baseline: £46.29m
Forecast: £46.46m
Variance: 0.40%
Variance text: n/a
Whole Life Cost: £139.13m
WLCost text: The Whole Life Costs will be updated through formal change control following the approval of the revised Business Case.
Notes1:
Notes2:
Sourcefile: IPA_2015.csv