2015 Report details for project: Immigration Platform Technologies (IPT)

Project name: Immigration Platform Technologies (IPT) - there are 5 reports for this project: 2015, 2016, 2017, 2018, 2019
Google search: Google search on project name (opens in new window) opens in new window
Organisation: HO (D16) - see all reports for this organisation
Report year: 2015 (data is from Sept 2014)
Category: ICT - see all reports for this category
Description: The Immigration Platform Technologies (IPT) Programme is providing the technology and information to support the immigration service now and in the future. UK Visas and Immigration (UKVI) Online Application Service: A single online application process for all visa and immigration services •Accessed via GOV.UK, for all in and out of country applications •Used to apply, pay and book an appointment •Replaces all of today’s online and paper-based application processes IPT Caseworking Tool: A modern, resilient caseworking tool for the Home Office •Core caseworking tool used in the Home Office (replacing legacy systems BRP, ICW, CID PBS, ASYS) •Configurable technology modules tailored to specific business areas needs •Automates existing manual, paper-based processes and provides supported decision-making to drive consistency Person Centric Data Platform: An integrated platform providing a single view of customers and their history •Combines sources of customer information into a single, resolved identity •Allows access to biographic and biometric information on our customers and their history •Enables effective day to day activity monitoring and production of management information.
DCA (RAG): Amber
DCA text: An action plan to address the review recommendations is in progress and reviewed by the programme board on a monthly basis. The reasons for this rating are: • Timescales for the programme are challenging, the Programme continues to work with suppliers to address and improve the speed of delivery. • This is the first large scale Agile programme delivered within the Home Office, new ways of working are being developed and the programme is refining the delivery approach with its suppliers.
Start date: 2013-04-01
End date: 2017-03-31
Schedule text: The programme is on track but with limited contingency in the schedule.
Baseline: £77.64m
Forecast: £54.85m
Variance: -29.40%
Variance text: The programme is within agreed tolerance. Optimism Bias has not been utilised.
Whole Life Cost: £208.66m
WLCost text: The whole life cost forecast for the programme is within the agreed envelope.
Notes1:
Notes2:
Sourcefile: IPA_2015.csv

Home Selection Search All Reports All Projects (+dates) All Projects (+costs) All Organisations All Years All Categories


Acknowledgement: GMPP data has been re-used under the Open Government Licence.