2017 Report details for project: Tate Modern Project

Project name: Tate Modern Project - there are 5 reports for this project: 2013, 2014, 2015, 2016, 2017
Google search: Google search on project name (opens in new window) opens in new window
Organisation: DCMS (D5) - see all reports for this organisation
Report year: 2017 (data is from Sept 2016)
Category: Infrastructure - see all reports for this category
Description: The New Tate Modern will provide London with a unique public space for a rich collection of international art, combined with educational initiatives for diverse audience groups. The New Tate Modern will significantly enhance the UK's reputation as a major cultural force in the world.
DCA (RAG): Green
DCA text: Final recommendations have been met and programme has now completed.
Start date: 2010-01-01
End date: 2016-12-31
Schedule text: Programme has now completed
Baseline: £12.90m
Forecast: £10.90m
Variance: -16.00%
Variance text: The final cost is £2m lower than Baseline.
Whole Life Cost: £271.00m
WLCost text: The anticipated final cost is £269m.
Notes1: The Tate Modern Project
Notes2:
Sourcefile: IPA_2017.csv