2017 Report details for project: Priority School Building Programme - Private Finance

Project name: Priority School Building Programme - Private Finance - there are 4 reports for this project: 2015, 2016, 2017, 2018
Google search: Google search on project name (opens in new window) opens in new window
Organisation: DFE (D6) - see all reports for this organisation
Report year: 2017 (data is from Sept 2016)
Category: Infrastructure - see all reports for this category
Description: To rebuild 46 of the schools in the worst condition across England through Private Finance
DCA (RAG): Amber/Green
DCA text: Private Finance team continue to closely monitor contractor performance to ensure schools are handed over to schools in suitable condition. To date construction is complete on 32 of the 46 schools.
Start date: 2011-07-19
End date: 2043-07-01
Schedule text: No deviation from planned schedule
Baseline: £329.90m
Forecast: £326.86m
Variance: -1.00%
Variance text: Budget variance less than 5%
Whole Life Cost: £2,153.04m
WLCost text: The CDEL forecast changed in 2016/17 as it now include the CDEL scores for the Aggegator Vehicles's (AV)) own financial assets (loans to Borrower SPVs). DfE reached agreement with HMT in Autumn 2016 that the AV had a net CDEL score through removing the CDEL score for the AV's financial liabilities.
Notes1:
Notes2:
Sourcefile: IPA_2017.csv