2017 Report details for project: Queen Elizabeth Programme

Project name: Queen Elizabeth Programme - there are 7 reports for this project: 2013, 2014, 2015, 2016, 2017, 2018, 2019
Google search: Google search on project name (opens in new window) opens in new window
Organisation: MOD (D17) - see all reports for this organisation
Report year: 2017 (data is from Sept 2016)
Category: Military - see all reports for this category
Description: To deliver 2 Queen Elizabeth Class aircraft carriers.
DCA (RAG): Amber
DCA text: The IPA described seeing much progress since the last review, its Amber assessment was based on issues around: HMS Queen Elizabeth’s First Entry to Portsmouth (FEP); cost clarity; manning requirements; the Common Support Model (CSM) business case and support in the Solent when unable to enter port. These actions are being progressed through the stakeholders and included in Holding to Account discussions. FEP will now be a comparatively low key event with a later ceremonial event. A comprehensive assessment of Programme costs has been produced. Manning is being successfully managed based on continued prioritisation. Plans for support in the Solent will be implemented as we gain experience of operating HMS Queen Elizabeth from her home port.
Start date: 1998-12-01
End date: 2023-03-31
Schedule text: Challenges exist within HMS Queen Elizabeth’s near-term schedule, with technical issues on several systems presenting risk to the Ships Staff Move-on Board and Ready for Sea Date programme milestones. The Ship’s Company and Aircraft Carrier Alliance are working closely to manage these serials. HMS Prince of Wales’ schedule has further to run and lessons from HMS Queen Elizabeth are being incorporated.
Baseline: £601.84m
Forecast: £593.27m
Variance: -1.00%
Variance text: Budget Variance less than 5%
Whole Life Cost: £7,400.08m
WLCost text: The Q2 estimated increase in cost of building the Carriers remains stable. Additional funding for the 10-year support budget change to operating one ship at Very High Readiness and one at High Readiness is being accounted for within Navy Command’s control total.
Notes1:
Notes2:
Sourcefile: IPA_2017.csv