2018 Report details for project: Great Western Route Modernisation (GWRM)

Project name: Great Western Route Modernisation (GWRM) - there are 3 reports for this project: 2017, 2018, 2019
Google search: Google search on project name (opens in new window) opens in new window
Organisation: DFT (D9) - see all reports for this organisation
Report year: 2018 (data is from Sept 2017)
Category: Infrastructure - see all reports for this category
Description: The Great Western Route Modernisation is an extensive programme undertaken by Network Rail and other key stakeholders to modernise existing infrastructure on the Great Western mainline - it will create faster more reliable services better stations and increased freight capacity. Modernising the route will improve the experience of everyone who uses it and stimulate economic growth in the south west and beyond.
DCA (RAG): Amber/Red
DCA text: Improved governance and programme management are resulting in the integrated industry approach. Since Sir Peter Hendy's report all major milestones have been achieved. Intercity Express Trains have been successfully introduced on the route, and electric services are now running between Didcot and Paddington. After the National Audit Office and Public Accounts Committee recommendations the business case has been revised and the decision was taken to reduce the scope of electrification.
Start date: 2011-12-01
End date: 2024-12-31
Schedule text: No deviation from schedule to report.
Baseline: £876.90m
Forecast: £789.90m
Variance: -10.00%
Variance text: The variation is due to a re-profiling of Network Rail spend from 2017/18 into Control Period 6 due to deferrals of scope announced in November 2016.
Whole Life Cost: £5,507.00m
WLCost text: Network Rail continues to carry out rigorous assurance on whole life costs to the Programme, including through regular Quantified Cost Risk Analyses, and variations in costs to individual elements are subject to a Programme and Portfolio level change request process.
Notes1: Great Western Route Modernisation (GWRM) including electrification
Notes2:
Sourcefile: IPA_2018.csv