2018 Report details for project: Visitor and Migrant NHS Cost Recovery Programme

Project name: Visitor and Migrant NHS Cost Recovery Programme - there are 4 reports for this project: 2016, 2017, 2018, 2019
Google search: Google search on project name (opens in new window) opens in new window
Organisation: DHSC (D12) - see all reports for this organisation
Report year: 2018 (data is from Sept 2017)
Category: Transformation - see all reports for this category
Description: To improve cost recovery from visitors and migrants (both EEA and non-EEA) in England to ensure that only those eligible receive free NHS healthcare.
DCA (RAG): Amber/Red
DCA text: Following the election the Programme has engaged with Ministers on an updated set of priorities, which include supporting better cost recovery performance within the NHS, delivering manifesto commitments on the Immigration Health Surcharge, and defining a post-EU exit cost recovery regime. Engagement with the leadership teams from NHS England and NHS Improvement to operationalise and embed upfront charging in both NHS and non-NHS trusts continues at pace, and working groups are fully established to take this forward. Nineteen NHS trusts have recommenced piloting to test models for implementing improved eligibility checking. The final report on the outcomes of the pilots will be completed in December 2017 and will inform advice to Ministers on next steps. The SRO has commissioned a senior stocktake of the Programme's IT strand to support more effective planning and resource allocation in this area in 2018/19. NHS Improvement continue to build their capability towards taking more direct responsibility for operational improvement support.
Start date: 2013-09-01
End date: 2019-03-31
Schedule text: The Programme will continue to support improve cost recovery until at least March 2019, following post-election ministerial steers for a two year programme of work, commencement of new regulations in late 2017 and to ensure that the health and care system is able to deliver the required policy following the UK's exit from the EU.
Baseline: £6.23m
Forecast: £6.18m
Variance: -1.00%
Variance text: Budget variance less than 5%
Whole Life Cost: £25.53m
WLCost text: The Programme's budget is agreed each year and will carefully consider its bid for 2018/19 in light of current agreed objectives
Notes1:
Notes2:
Sourcefile: IPA_2018.csv