2019 Report details for project: T Level Programme

Project name: T Level Programme - there is only one report for this project
Google search: Google search on project name (opens in new window) opens in new window
Organisation: DFE (D6) - see all reports for this organisation
Report year: 2019 (data is from Sept 2018)
Category: Transformation - see all reports for this category
Description: To increase the economic value of skills being supplied by the post 16 system, increasing take-up of high quality qualifications to improve skills, increasing productivity and social mobility. To enable the sustainable delivery of new high quality T Levels for 16-19 year olds.
DCA (RAG): Amber/Red
DCA text: Delivery confidence for the T Level Programme remains at Amber Red, due to the complexity and interdependency of the programme on internal and external factors. Significant success has been achieved against an extremely tight timetable, meeting all our major milestones. However, significant challenge remains in upskilling the FE workforce, securing further capital funding for future delivery beyond 2020 and whether funding levels will be sufficient to incentivise providers to continue to engage with T Levels. Risk remains on the ability to ensure that industry placements are available to support every student who applies for a T Level qualification, and we will need to monitor the impact of these flexibilities closely on the programme.
Start date: 2016-10-25
End date: 2023-09-30
Schedule text: There has been a very significant amount of effort applied to maintaining the delivery schedule, and we have met all of our key milestones, including our two first 'go / no go' points. Working collaboratively with delivery partners, we launched the ITT for the development of the 2020 qualifications and subsequently awarded contracts to Awarding Organisations to develop the first three T Levels. We remain on track to meet our next key 'go / no go' point in Feb 2020 with the approval of the first three qualifications.
Baseline: £50.00m
Forecast: £50.00m
Variance: 0.00%
Variance text: Budget variance less than 5%
Whole Life Cost: £146.20m
WLCost text: Costs set out are those for the T-Levels programme as set by HMT at the 2017 Spring Budget. We have no confirmed budgets past Financial Year 2019-20. Future budget will be set in the next government spending review.
Notes1:
Notes2:
Sourcefile: None