2019 Report details for project: Digital Railway

Project name: Digital Railway - there is only one report for this project
Google search: Google search on project name (opens in new window) opens in new window
Organisation: DFT (D9) - see all reports for this organisation
Report year: 2019 (data is from Sept 2018)
Category: Infrastructure - see all reports for this category
Description: Accelerating and supporting the delivery of digital technologies on our railways.
DCA (RAG): Amber
DCA text: This scheme is currently rated Amber due to most schemes still being in the early development stages and new territory. The programme is being monitored closely and we expect delivery confidence to improve as schemes mature.
Start date: 2016-11-23
End date: 2023-04-01
Schedule text: The projects within this Portfolio are still set for completion by the Project End Date.
Baseline: £32.00m
Forecast: £32.02m
Variance: 0.00%
Variance text: Budget variance less than 5%
Whole Life Cost: £450.00m
WLCost text: The funding provided as part of the National Productivity Investment Fund (NPIF) in the 2016 Autumn Statement was £450m. We will continue to assess the costs of the Programme and scope of projects in order to remain in the funding provided.
Notes1:
Notes2:
Sourcefile: None

Home Selection Search All Reports All Projects (+dates) All Projects (+costs) All Organisations All Years All Categories


Acknowledgement: GMPP data has been re-used under the Open Government Licence.