Reports for project: High Speed Rail Programme (HS2)

Report Details Year Organisation DCA status     Start date     End date Base £m Fcast £m Variance% WLCost £m   Category
Details 2013 2013 DFT Amber/Red 2011-02-28 2033-12-31 306.8 209.0 -31.9 1,117.9   Infrastructure
Details 2014 2014 DFT Amber/Red 2011-02-28 2033-12-31 347.6 347.6 0.0 42,600.0   Infrastructure
Details 2015 2015 DFT Amber/Red 2011-02-28 2033-12-31 380.0 483.0 27.1 42,559.5   Infrastructure
Details 2016 2016 DFT Amber/Red 2011-02-28 2033-12-31 713.0 713.0 None 42,559.5   Infrastructure
Details 2017 2017 DFT Amber/Red 2011-02-28 2033-12-31 928.6 928.6 0.0 55,700.0   Infrastructure
Details 2018 2018 DFT Amber/Red 2011-02-28 2033-12-31 1,845.8 1,845.8 0.0 55,700.0   Infrastructure
Details 2019 2019 DFT Amber/Red 2011-02-28 2033-12-31 2,976.0 3,009.0 1.0 55,700.0   Infrastructure

Totals: 7 annual reports

Select Details to see the full report for that year. Select Year to see all reports for that year. Select Organisation to see all projects for that org.


National Audit Office and Other related links: Source Date Notes
High Speed Two: A progress update NAO Jan 2020 Report raises concerns re project costs.
Investigation into land and property acquisition for HS2 NAO Sep 2018
Progress with preparations for High Speed 2 NAO Jun 2016
High Speed 2: A review of early programme preparation NAO May 2013